During the 12th week of this project, the cabinets that have been built off-site are being assembled in the Lear Center. Here is the tall vertical display unit built for the new reading room. The unit will be lighted within and enclosed by glass.

The top portions of the cabinets along the north wall of the reading room have been put in place. The shelves and doors have not been added yet.

The refinishing of the old woodwork in the Palmer Room is done. The color is much lighter now and closer to the finish of the new cabinets in the reading room.

Out in the hallway, the lockers are being installed. The lockers are intended as a place for researchers using the resources in special collections and archives to put their personal belongings.